FREE MANUFACTURING CALCULATOR

Production Target Calculator

Estimate hourly and daily garment production targets from SMV, manpower, working hours and expected line efficiency.

Standard minutes required per garment
Number of operators/workers included
Net planned working hours
Expected production efficiency

Formula

Daily target = (Manpower × Working hours × 60 × Efficiency) ÷ SMV.

Worked example

With 40 people, 8 hours, 55% efficiency and an 18-minute SMV, the estimated daily target is about 586 pieces.

Frequently asked questions

What is SMV?

Standard Minute Value is the standard time allocated to produce one garment or operation under defined conditions.

Why include efficiency?

A line rarely converts every available minute into standard output. Efficiency adjusts the theoretical capacity to a realistic planning level.